Field Notes Power

The grid is the schedule

Construction takes 18 to 30 months. Getting power to the site can take years longer. Plan the data center around the interconnection, not the other way around.

Elyas Jazayeri, Ph.D. · October 2026 · 3 min read

For most of the last decade, the hard part of building a data center was the building. AI changed the order. On most large campuses today, the gating item is not steel, concrete, or even chips. It is how fast the utility can deliver power to the site.

A hyperscale building can go from groundbreaking to ready in roughly 18 to 30 months. The utility work that feeds it can add years on top of that. Teams that plan the building first and the power second end up with finished buildings and nothing to plug in.

Why interconnection takes so long

A new load of a hundred megawatts or more is not a routine service request. Before a utility can commit, it has to study how the new load affects its system. Those studies often show that serving it needs new transmission lines, a new or expanded substation, or upgrades further upstream.

Each of those is a construction project of its own, with its own permits, its own land questions, and its own equipment queue. And in many regions, a long line of other large-load requests is waiting for the same studies and the same upgrades. None of this moves at the speed of a building contractor.

The dark shell problem

When the building wins the race, you get a dark shell: a finished, commissioned-ready facility waiting on energization. Capital sits idle. Equipment warranties start running on gear that has never carried load. Commissioning teams demobilize and have to be brought back. The cost is real even though nothing on site is broken.

The fix is not to build slower. It is to sequence everything against the energization date instead of the start date.

Plan in this order

  1. Secure the power path first. Let available capacity and a credible energization date drive site selection, alongside land, fiber, and water.
  2. Lock long-lead high-voltage equipment early. Main transformers and switchgear can take as long as the building. Their procurement belongs at the start of the schedule.
  3. Sequence the building to energization. Work backward from the date power arrives, and align construction, commissioning, and fit-out to it.
  4. Phase the capacity. Energize a first block on the power available now and add blocks as utility upgrades land, instead of waiting for the full load.
  5. Run one integrated schedule. The most common failure is three schedules, for the utility, the substation, and the building, that never meet. One owner should hold all three.

Questions to ask before committing to a site

  • How much capacity is available today, and how much depends on upgrades?
  • Is the energization date committed, or estimated?
  • Who builds the substation, and who owns the long-lead equipment?
  • Is there a phased path, such as interim capacity while upgrades are built?
  • What happens to the request if the load or design changes?

In AI infrastructure, the fastest builder is often the one who started the power conversation first.